Residents of Hamilton and the wider Northshore Brisbane precinct are advised that the May 2025 Street Renewal Program is still underway, with extensive civil works being carried out by BMD under the direction of Economic Development Queensland (EDQ).
Read: Transforming Hamilton: Northshore Vision 2050 to Redefine Brisbane’s Future
The works form part of the ongoing urban renewal and infrastructure improvement plan for the area and will continue throughout May. The key operations are divided across two major work zones.
Key Activities
Stage 1 Work Zone:
- Delivery and removal of plant, materials, and equipment
- Safe removal of hazardous materials, including asbestos
- Earthworks involving crushing, recycling, preloading and stabilisation of soft soils
Stage 2 Work Zone:
- Utility trenching and installation of stormwater and services
- Safe asbestos removal
- Demolition of the K Shed
Additional Works Across Both Zones:
- Trenching, backfilling, and service investigations
- Environmental monitoring
- Ongoing movement of equipment between sites
Work Hours
Construction is scheduled to occur Monday to Thursday from 6:30 a.m. to 6:00 p.m, and Friday and Saturday from 6:30 a.m. to 4:00 p.m. No work will take place on public holidays. These hours are in accordance with Brisbane’s construction regulations.
Residents should be aware of several impacts during this period. Traffic detours will be in place near the work zones and within the Northshore Brisbane precinct. For everyone’s safety, please follow signage and directions from traffic controllers. Noise, dust, and vibration will be generated by machinery such as excavators, haulage vehicles, concrete saws, crushers, and other heavy equipment. Measures will be in place to monitor and reduce these disruptions.
Read: Northshore Hamilton Cited as an Ideal Location for the Proposed Brisbane Seafood Market
There may be temporary interruptions to utilities and services as part of the Street Renewal Program. Any affected properties will receive advance written notice at least seven days prior to any disruption. An increase in workforce numbers and construction vehicle movements around the area is also expected.
Local residents are encouraged to stay informed and sign up for regular updates through the Northshore Brisbane Have Your Say webpage at: http://www.yoursay.edq.qld.gov.au/northshore.
Published 26-May-2025